Free field resources
Construction change order template
When the requested work changes, record the scope and price before the details get lost in texts. Use this checklist to prepare a clear proposal and capture the right approval.
No signup required. The blank text file can be copied into your document editor. The PDF is a worked example, not a blank form.
What to put in a change order
- Project and reference: job name, site, original contract reference, change number, date, contractor, and customer.
- Requested change: what is being added, removed, or revised; who requested it; and why. State exclusions so a short description does not become an open-ended promise.
- Price basis: agreed lump sum or time-and-material basis. Break out quantities, hours, rates, materials, equipment, and any separately agreed markup or tax.
- Schedule impact: additional days, dependencies, or “to be confirmed.” Do not imply there is no impact if it has not been checked.
- Approval: name, role, date, signature, and what the signer is acknowledging. Use the authorization required by your contract.
- Evidence and revisions: photos, drawings, written requests, and links to the previous signed version.
Worked example: kitchen circuit reroute
Request: Relocate the kitchen outlet circuit to the revised cabinet position shown by the customer.
Included: 3.5 hours of electrical labor and the listed cable and fittings. Wall finishing and additional circuits are excluded.
- Labor: 3.5 hours × $85
- $297.50
- Materials
- $86.40
- Illustrative subtotal
- $383.90
Example only—not a recommended rate or estimate for your job. No markup or tax is included. Confirm schedule impact and any required charges before asking for approval.
A simple approval workflow
- Describe the requested change and attach the relevant evidence.
- Review the scope, amount, exclusions, and schedule impact with the authorized person.
- Capture approval using the process required for that project. Do not mark a draft as approved because it was merely sent.
- Keep the signed original. If the scope changes again, create a clearly numbered revision and request fresh approval.
- Send the record to the customer and your office; connect it to the later invoice without claiming it is itself proof of payment.
Change order or T&M ticket?
A change-order record describes a proposed or approved scope/price change. A T&M ticket records labor, materials, and equipment used in the field. A project may require both. Keep the acknowledgment of field quantities separate from final authorization to change the contract price.
These examples help organize records; they are not legal advice or a substitute for the approval process in your contract. A field signature does not automatically authorize a contract-price change.
Related: Time and material ticket template